Artificial intelligence
Oracle Invoked Force Majeure on a Stargate Data Center. The Thing That Failed Was a 17-Mile Pipeline
Oracle told Blue Owl's Stack Infrastructure it should not have to step up to full rent if the 2.45-gigawatt Project Jupiter campus misses 2028. The delay has nothing to do with chips — it is a right-of-way dispute and an air permit.
MAI
Oracle sent a force majeure notice on Thursday to Stack Infrastructure, the Blue Owl Capital unit building Project Jupiter — the 2.45-gigawatt campus in southern New Mexico that is one of the flagship sites of the $500 billion Stargate program with OpenAI and SoftBank. Bloomberg reported the notice first; Reuters confirmed it through a person familiar with the matter. Oracle shares fell about 4 percent on the day, with CNBC putting the decline at 3 percent. Blue Owl fell roughly in line and Bloom Energy, which is supplying the site's fuel cells, dropped about 6 percent.
Both companies say nothing is wrong. "Project Jupiter remains on our planned schedule," Oracle said. "We are fully committed to New Mexico and confident in our path forward." Blue Owl said the notice "does not change the financial commitments to this multi-year project." Those statements can be accurate and the notice can still matter, because of what a force majeure clause does inside a lease of this shape.
What the notice actually does
Oracle is not trying to leave. It cannot: the lease has no exit for the tenant. What a force majeure notice buys is time on the rent schedule. Under the structure Reuters describes, Oracle pays a lower development-stage rent while the campus is being built and steps up to a much higher completion-stage rent once it is delivered. If delivery slips past the 2028 target and the delay is excused, Oracle stays on the cheap rent for longer. It is a claim on the timing of the obligations behind roughly $18 billion of project debt, not on their existence — and Bloomberg notes it is not certain the maneuver frees Oracle from anything at all.
The detail that makes this awkward is whose job the power was. Reuters reports that under the contract Oracle is responsible for procuring electricity for the campus. The notice is a request to be excused from the consequences of a delay in the thing Oracle itself was meant to deliver.
The constraint is a pipeline, not a chip
| Site | Doña Ana County, New Mexico |
| Capacity | 2.45 GW — roughly 1.8 million homes |
| Developer | Stack Infrastructure (Blue Owl Capital) |
| Anchor tenant | Oracle |
| Target online | 2028 |
| Debt | ~$18 billion, roughly 20 lenders |
| Sponsor equity | ~$3 billion (Blue Owl) |
| Generation | Bloom Energy solid-oxide fuel cells, gas-fired |
| Gas supply | Energy Transfer's 17-mile "Green Chile" line — slipped from August 2026 to February 2027 |
Project Jupiter does not draw its power from the grid. It burns gas on site in Bloom Energy fuel cells, a design chosen partly because it uses very little water in a state that has very little to spare. That choice made the campus dependent on a single 17-mile pipeline, and the pipeline is the thing that failed. The New Mexico State Land Office repeatedly denied right-of-way across state trust land, the route was redrawn, and in-service slipped from this past August to February 2027 — close to six months. A separate air-quality permit for the fuel cells faces a state deadline in late November.
None of the usual AI bottlenecks appear anywhere in that paragraph. There is no shortage of accelerators here, no memory allocation problem, no fab capacity story. A 2.45-gigawatt AI campus is being held up by a right-of-way dispute over seventeen miles of state land and an air permit.
Who is carrying the risk
This is where the notice stops being a contract dispute and becomes an industry signal. Blue Owl put roughly $3 billion of equity into Project Jupiter and raised about $18 billion in loans from some twenty banks. That debt now trades below 90 cents on the dollar, according to Bloomberg — lenders were already marking the timeline down before Oracle put anything in writing.
The financing model behind the current data center buildout assumes a creditworthy hyperscale tenant signs a long lease, the developer borrows against that lease, and the rent arrives on schedule. Oracle's notice tests the one joint in that structure that had never been tested at this scale: what happens when the building is late for reasons nobody in the deal controls. If a tenant can hold the low rent through a delay, the delay lands on the developer and its lenders, and every project financed on the same template gets repriced a little.
What it turns on
Oracle's own numbers make the stakes plain. The company reported $664 billion in remaining performance obligations last quarter, up $209 billion year over year — a backlog that only converts into revenue if the buildings exist. Project Jupiter is one campus, but it is the one where the physical world pushed back hardest, and it is doing so while local opposition to the site turns into a midterm election issue.
The story of AI infrastructure for the last two years has been a story about silicon. This is the quarter it becomes a story about land, gas, and state permits — and about which party to a multi-year lease absorbs the cost when those take longer than the spreadsheet said.
Sources: Bloomberg: Oracle Cites 'Force Majeure' to Shield Itself on Controversial Data Center · Reuters via CP24: Oracle triggers 'force majeure' on data centre project over power delays · TechCrunch: Oracle sends force majeure notice on its New Mexico Stargate data center · CNBC: Oracle sends 'force majeure' notice about data center project · Investing.com: Oracle triggers force majeure on massive 'Project Jupiter' data center · STACK Infrastructure: Delivers Digital Infrastructure for Data Center Campus in New Mexico · OpenAI: Five new Stargate sites